| West Jordan 3rd District Court |
|
|
| Images |
|
|
| Description
of Project |
•Installation of single-ply roofing over rigid insulation with custom fabricated copper roofing and flashings. |
| Scope of the Project |
Contract Amount |
| •38,000 Sq. Ft. |
•$170,000.00 |
| Project Manager |
General Contractor |
•Paul Seppi
•Jim Ritchie |
•Okland Construction |
| Affiliates |
Owner |
•Firestone - Single-ply roofing
•Integris Metals - Copper
•LM Curbs - S-5 Sno-Rail |
•West Jordan City |
Challenges
Associated With The Project |
•Installation of copper flashings in conjunction with single-ply roofing.
•Installation of EIFS coatings and masonry facades. |