Remove and replace existing built up roofing system
with new tapered insulation and Johns-Manville built-up roof membrane.
Including, intricate sheet metal work and new building lighting features
provided by subcontractor.
Scope of the Project
Contract Amount
50,000 Sq./Ft. built up roofing
10000 Sq./Ft. of deck coatings
10,000 Sq./Ft. of EPDM single-ply
Various specialty sheet metal.
$750,000.00
Project Manager
General Contractor
Andy Seppi
Utah Tile & Roofing, Inc.
Affiliates
Owner
Johns-Manville
Utah Correctional Industries
State of Utah Division of Facilities Management
Challenges
Associated With The Project
Corrdinating removal of asbestos containing felts with
the prison labor provided by Utah Correctional Industries. Coordinating
roofing work with the facilities manager to avoid conflict with the
many daily activities at the Capitol.